departure from uao – april 15, 2026
The Constellation has departed from UAO and is enroute to Texas.





continuation workscope – march 4, 2026
The rework on the heating and AC systems continues. Galley drawer inserts are being installed. Main cabin drink rail tops are being prepped for future installation of the executive foldout tables. Work on entertainment screen bezels continues. The executive foldout table surrounds are in work. The forward cabin electrical cabinet face plate is being reworked to incorporate a cover for the control panel.












continuation workscope – february 25, 2026
Work on the drawer inserts for dishware drawers continues. Structures is assisting in the fire-proofing of the APU compartment. The flux gate for the GI 275 installation has been completed. Latches for the fold out executive tables are in work.










continuation workscope – february 11, 2026
The new main cabin bar control panel is being fit to the bar. Bill Sandman has arrived to do some heater rework, and the AC controllers have been relocated. Wiring for the avionics upgrade continues.





continuation workscope – february 11, 2026
Entertainment screen bezels are being reworked. Wiring is being run for new magnetometers. The conference room divan surround rework continues. Structure is being installed in the main cabin drink rails to accommodate the executive fold out table installation. The entertainment system screens have been fixed. Relocation of the flight deck headset jack locations is in work.









continuation workscope – february 4, 2026
The main cargo door dress panel is being reworked, and h-channels installed. Drawer inserts for dishware drawers in the galley are getting leather wrapped. The AC control wire bundles are being reworked and reinstalled.







Continuation workscope – january 28, 2026
The privacy curtain has been remade and test fit to the airframe. Mockups for the executive fold out tables have been fit to the main cabin. Troubleshooting for the main cabin entertainment system screen signal issue is in progress. The stateroom coat closet has been adjusted to close the gap between the closet back and the sidewall.













Continuation workscope – january 21, 2026







Continuation workscope – january 14, 2026
The Constellation has returned to Aurora. Protection and removal of interior components to facilitate further maintenance.












WINTER 2025 WORKSCOPE
The team have arrived in Montrose to prep the aircraft for her return to Aurora later this month.




interiors – july 9, 2025
Final installation of the interior continues.











interiors – july 2, 2024
The final installation of the interior has begun.





























structures – june 25, 2025
The conference room divan frame is in work and being fit to the surround cabinets. The stateroom aft bulkhead panels are in work. Baggage liner is being installed. Work continues on window buckets. Potted inserts have been installed in the air show bar countertop.








interiors – june 25, 2025
Work on covering the conference room divan surrounds continues. Headliner panels are being installed in the main cabin. Work on main cabin curtains. The stateroom aft bulkhead panels are being covered. Bulkhead face panels and overhead and windowline panels are being installed.

















Structures – June 18, 2025
The conference room divan surround cabinets are being fit to the aircraft, with cubbies and countertops being installed. The emergency exit chute has been fit and tested. Work continues on the air show bar.














electrical – june 18, 2025
The flight engineer station screen has been wired to be able to select different camera views. Mocketts hiding 110AC sockets are being assembled, and will be installed in the conference room, main cabin, main cabin bar, and stateroom. The Astronics moving map has been installed. Wire for the black water tank level sensor is being run, as is wire for the under-floor A/C cassettes.















Interiors – june 18, 2025
Forward cabin curtains have been installed. The dress panels for the aft lavatory outer bulkheads have been installed. Carpet padding and carpet are being test fit and trimmed to the forward cabin. H-channels continue to be finished.









structures – june 11, 2025
The conference room divan surrounds are being assembled. The aft lavatory aft bulkhead closeout is in work. Entertainment system screen bezels are being manufactured. The aft bulkhead panels are in work.






heating and air conditioning – june 11, 2025
The flight deck AC cassette is being installed. Ducting continues to be installed for fresh air and air conditioning throughout the aircraft. Heaters are being installed. The air conditioning compressors have been installed.












electrical – june 11, 2025
Emergency Exit lights and reading lights are being installed in the main cabin valance panels. Main cabin environmental controls have been installed behind the bar. The conference room entertainment system screen has been ops checked. The warming ovens and beverage warmer have been fit checked. Conference room dome lights have been installed and ops checked. Forward cabin valance panels have had emergency exit lights, reading lights, downwash lights, and speaker covers installed. The left-hand forward cabin valance panel has been installed.The forward lavatory sconce lights have been installed and ops checked.

















interiors – june 11, 2025
Carpet has been installed in the forward cabin. Carpet and padding are being cut for other zones in the airplane. The conference room divan surrounds are being covered. Panels for the airshow bar are being covered. The map has been installed in the conference room.









structures – june 4, 2025
Window buckets are being installed in the aircraft. The air show bar face has been installed. The aft lavatory cabinets have been installed to facilitate the final fitting of side panels. The conference room divan and divan surrounds are being fit. The forward lavatory cabinetry and drink rails have been installed.








heating and air conditioning – june 4, 2025
Ducting for heating and air conditioning continues to be installed in overhead valance panels throughout the cabin. Air conditioning system components are being installed.









electrical – june 4, 2025
Emergency exit lighting is being installed in the forward cabin valance panels. Lighting in the galley and forward lavatory has been ops checked.









interiors – june 4, 2025
Manufacturing of curtains continues. The bed frame has been covered with leather and grospoint. The stateroom bed mattress is in work. Carpet is being cut. Panels for the rear stateroom bulkhead face are being covered.

















structures – may 29, 2025
Skins are going on the airshow bar. Main cabin drink rails are being prepped for installation. Armrests for the forward cabin seats are finished. Potted inserts are being installed in the conference room table top.





interiors – may 29, 2025
Drawer faces are being covered.


structures – may 22, 2025














heating and air conditioning – may 22, 2025
Ducting installation continues



electrical – may 22, 2025








interiors – may 22, 2025





structures – may 14, 2025
Interior panels are being fit to the aft lavatory and stateroom prior to cover. Fresh water lines for the bar and aft lav have been installed on the aft lav bulkhead.





electrical – may 14, 2025
Conference room up and downwash light controls are installed. The conference room terminal board has been completed. Main cabin bar electrical bundle has been installed on the aft lavatory bulkhead. The galley and forward lavatory water heaters have been wired up.







interiors – may 14, 2025
The ship’s set of silverware has been polished. The galley to conference room pocket door is in finishes. The emergency exit door dress panel is being installed on the conference room emergency exit. Arm rests for the state room divan are in work. The forward cabin window line trim pieces are being installed. Printed samples for the conference room map have arrived.










structures – may 7, 2025
Forward lavatory and bar faces are coming back from paint. The forward lavatory cabinet is back from paint. Aft lavatory bulkheads are having potted inserts installed to support electrical lines and plumbing installation. Places for photo placards in the conference room credenza top have been routed out. Credenza drawer faces are being prepped for finish paint. The conference room divan backrest structure is in work. The A/C cassette has been built. Main cabin window buckets are getting prepped for paint. The aft lavatory countertop is being trimmed to fit. Countertops for the drink rails and aft lavatory sink are ready to cut.












heating and air conditioning – may 14, 2025
The air conditioning system compressor has been installed in the right wing.


electrical – may 7, 2025
The galley terminal board nearing completion. The in-flight entertainment system has been installed in the forward cabin electrical cabinet. The ELT has been relocated to the forward cabin electrical cabinet. The in flight entertainment system inverter and WiFi boxes have been installed. Wiring of the flight deck terminal board under the floor is in work. Heater fire detection circuit breakers, indicator lights, and switches are being test fit and wired to flight engineer’s panel








interiors – may 7, 2025
Main cabin headliners are being covered.


structures – april 30, 2025
Trim pieces for the main cabin bar have returned from being chromed. Plumbing is being installed in the galley cabinets. Window bezels are being manufactured. The toilet unit is being prepped for paint. The drink rail and right hand cabinet have been temporarily installed in the aft lavatory in order to fit the J-channels for the sidewall panels. Side and overhead panels are being fit to the aircraft prior to moving into finishes.











heating and air conditioning – april 30, 2025
Ducting and plenums for the heating and air conditioning are being manufactured.




electrical – april 30, 2025
The overhead galley cabinet wiring harness installations have been completed and are waiting on switch panels. Main cabin aisle light wiring is being installed. Work continues on the Galley terminal board installation.




interiors – april 30, 2025
The stateroom bed frame is being wrapped in leather.


structures – april 23, 2025












heating and air conditioning – april 23, 2025
Ducting for fresh air and air conditioning is being installed in the forward cabin. The heaters have arrived. The over wing air duct has been installed.





electrical – april 23, 2025
Potted inserts are being installed for galley freshwater and blackwater tank level sensors. Wiring has begun on the galley power distribution terminal board. The galley lighting control wiring harnesses are being installed in the aft upper galley cabinet.





interiors – april 23, 2025
Work on window line and bulkhead face panel covering continues.



structures – april 16, 2025
The forward lavatory vent screens are being formed and test fit. The refer cabinet has returned from finishes. The conference room divan surround cabinets are being assembled. The aft lavatory is in its final test fit prior to moving into finishes. The heat and A/C controller bracket has been assembled. Work on the Lazy Susan installation in the main cabin bar continues. The coat closet is being fit for the aft cabin closeout curtain. Door trim and hardware is being prepped to send out for plating.


















electrical – april 16, 2025
The arduino for the flight engineer display control is being programmed. The forward lavatory door indicator light is installed. The cabin PA and intercom expansion modules are being installed. The Lazy Susan lights are being tested.





Interiors – april 16, 2025
Work on window line and bulkhead face panels continues. The forward lavatory side and overhead panels have been installed for a final fit to the forward lavatory structure.









structures – april 9, 2025
The forward lavatory door indicator light is being installed. Refer cabinet lights and switches are being installed and tested. Overhead panel support brackets continue to be installed. Overhead speaker brackets have been installed, and speakers test fit. Lazy Susan parts for the main cabin bar have arrived. The aft lavatory mirror surround is being prepped for finishes.








heating and air conditioning – april 9, 2025
Heater fire bottles are ready to install. Heat plenum prototypes are being test fit prior to manufacture.





electrical – april 9, 2025
Wiring of the cabin 110VAC inverter has been completed. The main cabin wire harness is being installed. Forward cabin wash light dimmers are being wired. Sconce lights have arrived from plating.





interiors – april 9. 2025
The main cabin bulkhead dress coverings are in work. Main cabin windowline panels are being covered with insulate and test fit before final covering, as are aft bulkhead dress cover panels. Fabric for the curtains has arrived.















STRUCTURES – april 2, 2025
The aft lavatory mirror surround preliminary construction is complete and fitment checks done. The aft lavatory cabinetry is being final fit checked before heading to the interior shop for leather wrap. The main cabin mini credenza has been completed, awaiting hardware from the platers. Main cabin headliner and window trims are being fitted. Fwd and aft lavatory doors are being outfitted with their electronics. The refrigerator cabinet has had its preliminary ops check complete and a final ops check is set for 4/4/25. Final assembly of the refer is prepped, awaiting final plated hardware.












heating and air conditioning – april 2, 2025






electrical – april 2, 2025
Power has been run to the main cabin relay and the main cabin inverter. The air stair control box has been test fit. CPCs have been added to the circuit breaker harness.





interiors – april 2, 2025
Valances and door faces continue to be covered.









cabinets and bulkheads – march 26, 2025
The valances have been final trimmed for final fit and have entered the interiors shop for upholstery. The main cabin coat closet has had its final in-ship fitment to the headliner panels and drink rail. Fitment trims have been made and is undergoing fine tune adjustments. The conference room trim has all been fitted and sent off to the chrome shop. The Conference room credenza received its final fit check and removed awaiting final install. The windowline panels are quickly getting their final fit checks and trim before being wrapped. The fwd lavatory cabinetry has had its final fit check with interior panels before heading off to finishes for paint. The headliner structure has made its way to the state room bulkhead and preparations are being made to install headliner panels for fit checks. The lavatory doors are being outfitted with their indicator lights and updated handles with electrical components. The aft lavatory plumbing components have begun population and the faucet mounting structure has been welded and installed. Lavatory mirrors have been sent to the manufacturer and are being machine cut. Countertops are going through quality inspection before being protective wrapped and stored, awaiting final installation.
The galley refrigerator cabinet has gone through preliminary paint and final assembly has begun. It is currently being bench tested with all the refrigeration equipment for final ops check.





















electrical – march 26, 2025
The main cabin wire bundle is in work. Autopilot wire bundles have been installed.






moving map – march 19, 2025
The Constellation 3D model has been uploaded to the moving map software.




cabinets and bulkheads – march 19, 2025
Aft Lavatory door frames are being custom fitted and trimmed. The Curved bulkhead is getting patterned and metal dress covering substrate cutting has begun. More curved honeycomb is being manufactured for the Conference room divan side cabinetry. Various parts are going into and coming out of the paint shop at an expedited rate. Galley sink cabinet is in the ship for the last time to get all its plumbing connections finalized and stainless lines run. Galley upper cabinets are prepped for finishes and the sheet metal faces have been sent to the paint shop. Countertops are getting their final prep and coat of Richlite sealer. The valances have been test fit for their final trim and are headed to the interiors shop for wrap.













electrical – march 19, 2025
The last of the autopilot wires are being finished. Up wash and down wash light rails are being wired and tested. The cabin power distributor box has been installed, and electrical cable run. The up wash and down wash light dimmers are being installed.






interiors – march 19, 2025
Conference room bulkhead face panels and the forward lavatory aft bulkhead face panel are being covered.





cabinets and bulkheads – march 12, 2025
Sidewall and overhead panels in the forward lavatory are being fit before going into finishes. Work continues on installing main cabin and conference room overhead panel attach structure. Door trim is being fit with the pocket doors for the galley to conference room door and the forward lavatory door. The drain line for the refrigerator is being fit to the refrigerator cabinet.











heating and air conditioning – march 12, 2025
Rerouting of air stair door hydraulic lines to accommodate air conditioning lines continues. Ducting is being mocked up in the main cabin. Installation of air conditioning lines continues.






interiors – March 12, 2025
The flight attendant seat frame has been test fit in place with cushions. Conference room overhead panels are being covered. Work has begun on forward lavatory dress panels.









cabinets and bulkheads – march 5, 2025
Finished galley countertop has been final fitted and fastener locations set in place. The FWD lavatory countertop is getting its trim fitted before the final coat of sealer is applied. Galley cabinetry has gone through its paint prep stages and the facias all fitted to be sent out for paint. Fresh water plumbing in the galley cabinetry has been routed and getting all its clamping locations sorted with the technical team. Main cabin mini credenza is ready for countertop sealing and being staged with completed monuments/cabinetry.











heating and air conditioning – march 5, 2025
Hydraulic lines for the air stair door are being modified to accommodate air conditioning lines. Air conditioning lines continue to be run.





electrical – march 5, 2025
The autopilot wire bundles are in work. The multi-view camera system for the flight engineer is being set up and tested.





interiors – march 5, 2025
Conference room headliner panels are being prepped for cover.


cabinets and bulkheads – february 26, 2025
Conference room credenza top has been bonded to its substrate and is being prepped for sealer. Door trim is being fit and dry installed to all bulkhead door openings. Emergency door breakaway headers have been made and are undergoing fit and function tests.



heating and air conditioning – february 26, 2025
Heaters are being fit to their attach points.




electrical – february 26, 2025
The cabin systems wire bundle is being installed to the circuit breakers. Autopilot wire bundles are in work. Wires are being installed on the galley control panel.







interiors – february 26, 2025
Galley side and overhead panels are being fit with galley cabinetry. The main cabin bulkhead face plates are being prepped for cover. The conference room divan frame has arrived.








cabinets and bulkheads – february 19, 2025
Camera mounts have been installed in the wheel wells. J-channel is being shaped to the forward lavatory countertop. The forward lavatory closeout panels are in work. The sidewall panel is being fit to the forward lavatory in preparation for covering. Attachment structure for the overhead panels in the conference room are being installed. Final fit and trim is being applied to the conference room credenza along with fitment of the interior panels. Air stair deployment system structure has been made and installed. The hydraulic ram is in place and ready for the attachment to the air stair.

















heating and air conditioning – february 19, 2025
Air conditioning lines continue to be run throughout the aircraft.



electrical – february 19, 2025
Cabin switch test panels are being fit – this includes air stair controls, galley controls, and bar controls. The circuit breaker panel wire bundle is being assembled. Overhead valence light wire bundles (including reading lights, exit lights, and ordinance lights) have been run. Entertainment system screens have arrived.









interiors – february 19, 2025
Overhead blankets continue to be manufactured. Hot water tank blankets are being manufactured and test fit. The conference room credenza printed leather panels are being wrapped and fit to the credenza top.












cabinets and bulkheads – february 12, 2025
The galley countertop is being test fit and trimmed.






water plumbing – february 12, 2025
Hot water tanks have arrived. The aft lavatory hot water tank is being fit to the lavatory structure.





heating and air conditioning – february 12, 2025
Air conditioning lines continue to be run.






electrical – febryary 12, 2025
The buss bar is being installed in the cabin power j box. Forward cabin wire bundles are beginning to be installed.






interiors – february 12, 2025
Blankets continue to be sewn for overhead panels. The photo panels for the conference room credenza top are being prepped for the printed leather.





cabinets and bulkheads – february 5, 2025
Work on the aft lavatory door continues. Potted inserts for the liquor cabinet have been installed. Galley cabinets are being fit with the upper side panels installed. Window surround panels continue to be fit and prepped for covering. The forward lavatory countertop has been test fit. Material for the lazy-susan is being prepped for cutting.












heating and airconditioning – february 5, 2025
The air conditioning tubes have arrived, and installation has begun.


electrical – february 5, 2025
Work on the main cabin circuit breaker panel continues.


interiors – february 5, 2025
The galley backsplash is beginning to get installed. Overhead panels in the galley are being fit with the galley cabinets. Work on covering lavatory and remaining galley hallway panels and headliners continues. The main cabin door panel is being prepped for finishes.














cabinets and bulkheads – january 29, 2025
Stateroom and aft cabin windows have been installed and sealed. The trim for the Conference room credenza has had its final fit and trimming after welding the ends closed. Progress on the main cabin drink rails continue, the preparations for executive tables are well into development. Galley and forward lavatory cabinet prep work continues before heading to paint and finishes. The countertop for the forward galley is being formed and test fit. The Waterford crystal has arrived and the CAD models for the lazy susan/bar have been adjusted to fit. The conference room credenza photos have been printed on leather and trimmed. The inlay panels have been sent to laser cut. Refrigeration equipment has arrived. The refer cabinet has returned to the bench to receive all the equipment for test runs. A limit switch is being installed to disconnect the air stair deployment if the cargo door is closed.






























heating and air conditioning – january 29, 2025
Scat tube is being run for heating and AC.






electrical – january 29, 2025
The liquor cabinet lighting has been tested. Decanter shelf mechanism is awaiting its last few linkage and locking components. The main cabin entertainment screen has been tested. Bar and coat closet lighting have been installed and tested. Custom sconce light components have arrived and a bench test unit has been assembled. Galley overhead cabinet wiring harnesses have been built and are being test fit to the cabinets. The cabinetry team is installing the last of the threaded inserts for the harnesses and electrical equipment. Electrical switch panel blanks have been laser cut and populated for test fitting and wire harness construction. Air stair control panel test fit















interiors – january 29, 2025
The Interior shop has wrapped the remaining bar components in leather. The bar moves onto technical team for plumbing before heading to finishes for paint. Door panels continue to be covered.






Cabinets and bulkheads – january 22, 2025
Galley and forward lavatory cabinetry has gone into paint prep. Forward and main cabin bulkhead doors are being prepped and receiving their dress coverings. Main cabin window-line panels are being prepped for finish. The vacuum forming buck for the forward lavatory countertop is being built. Aft lavatory toilet surround is getting its final fit and trim before going to the interior shop. Refrigeration equipment is en-route and the cabinet is being prepped to receive the components.











heating and air conditioning = january 22, 2025
The heater attach brackets and heater mock up have been test fit. Work on the HVAC plenums continues





electrical – january 22, 2025
The main cabin relay has been installed. Wire bundles for the flight deck are being assembled. The peg board for manufacturing the galley electrical harness has been set up. The forward cabin terminal block has been test fit. Isle lighting has been tested. The air stair and door control electrical harness is being installed. Landing gear camera wires are being run.








interiors – january 22, 2025
Leather continues to be applied to components of the bar and door dress coverings. The liquor cabinet has been fabricated and decanter retention upholstery has begun.








cabinets and bulkheads – january 15, 2025
Work on the aft lavatory pocket door trim continues. The pocket door for the stateroom has been installed. The galley cabinets are being prepped for paint and covering. New closeout panels for the forward electrical cabinet are being trimmed and sent to Interiors for covering.









electrical – january 15, 2025
The forward baggage terminal strip has been relocated to accommodate the fresh water tank and plumbing, completing the splitting and relocation of the previous terminal strip. The “Lavatory Occupied” light circuit has been tested. The main cabin light control panel and air stair door control panel are in work. The galley switch panels have been designed.





interiors – january 15, 2025
The main cabin bar drawers are being covered. Quilted blanket is being installed on the forward electrical cabinet faces.






cabinets and bulkheads – january 9, 2025
The bar countertop has been sealed. Drink rail sidewall panels are being fit in preparation for covering. The lower sidewall panels around the windows are also being prepped for covering, and curtain rails are installed. Door trim pieces are in work. Work continues on the aft lavatory pocket door.












heating and air conditioning – january 9, 2025
Mock-ups for the HVAC system plenums are in work, and existing plenums are being fit to ducting.





Electrical – january 9, 2025
The aft baggage terminal strip has been relocated to accommodate the fresh water tank. The circuit breaker panel is being fit to the refrigerator cabinet, and channels to accommodate wire bundles are being installed. Dome and sconce lights are being soldered.









cabinets and bulkheads – december 31, 2024
The aft lavatory door has been installed and the outer bulkheads reinstalled. The trim has been permanently installed in the bar countertop, and the bar countertop is being sealed. Work on the stateroom bed frame continues, and it is being test fit in the stateroom.












heating and air conditioning – december 31, 2024
The team met with Bill Sandman to discuss ducting today.

electrical – december 31, 2024
The bench test for the in-flight entertainment system has been set up. Wiring diagrams for up wash and downwash lighting in the main cabin are in work. A new panel for the electrical cabinet has been manufactured to accommodate the in-flight entertainment system control panel.



cabinets and bulkheads – december 18, 2024
Structure for the stateroom bed is in work. Aft lavatory cabinets are being test fit in the aircraft. The main cabin bar has the sink fit and countertops installed. Potted inserts for door hardware are being installed and door gaps are being set on the refrigerator. Accent trim is being mocked up on the conference room credenza and the main cabin bar.












heating and air conditioning – december 18, 2024
Work on the mounting structure for the heater continues. The heating, fresh air, and air conditioning ducting is being mapped out in the airplane. Green tape denotes fresh air, blue tape denotes air conditioning, and red tape denotes heat.






electrical – december 18, 2024
Work on main cabin wire bundles continues. The inverters have arrived and are being prepared for testing.


interior updates – december 18, 2024
Window bezels for the forward lavatory are being covered. Quilting of materials for side panels and overhead blankets continues.






cabinets and bulkheads – december 12, 2024
Closeout panels for the main cabin bar are being formed. Potted inserts are being installed on the bar, as well as trim pieces. The bar is being prepped for finishes. Mounting brackets for the bar are installed on the aft lavatory bulkhead. The countertop for the main cabin coat closet has been sealed and trim installed. The in flight entertainment system screen has been test fit to the main cabin coat closet.


















heating and air conditioning – december 12, 2024
Old ducting is being removed to help facilitate work on the heating and air conditioning systems. Mounting brackets for the heater are being mocked up.



electrical updates – december 12, 2024
Galley control panels are being mocked up. The cabin intercom wire bundles have been made.



interior updates – december 12, 2024
Conference room valences are being covered. The forward lavatory overhead blankets are in work. The forward cabin side panels around the emergency exits are being covered. Forward cabin overhead valences are covered with leather and electronic components are being test fit.









cabinets and bulkheads – december 4, 2024
Tambour doors for the forward lavatory are being assembled and installed. Work on electrical support brackets in the overhead galley cabinets continues.








heating and air conditioning – december 4, 2024
Manufacture and installation of heater fuel lines continues, with lines being run to the fuel filters.





interior updates – devember 4, 2024
The astrodome bezel has been finished and installed. Bezels for the reading lights are being covered in leather. The forward cabin overhead valences are being prepped for and covered in leather.











cabinets and bulkheads – november 26, 2024
The sink has been test fit to the main cabin bar, and supports for the bar countertop are in work. The forward lav cabinetry is being edge filled and prepped for finish. The forward overhead galley cabinet has been modified to accommodate electrical work, and skates have been installed for the beverage warmers and mini ovens.








electrical updates – november 26, 2024
Work on the air stair control wiring continues. Astronics and Flight path 3D, the companies we have been working with on a moving map solution for the last 3 months, came to do a site visit. The main cabin relay has arrived.







INTERIOR UPDATES – NOVEMBER 26, 2024
Forward cabin overhead valences have been covered with foam in preparation for leather. The reading light bezels have been prototyped. The blanket for the forward cabin J-box is in work.











cabinets and bulkheads – november 20, 2024
Bar countertop, fabricating edge trim. Laminating countertop assembly. Edge finishing of wine & liquor cubby. Aft lavatory side ledge finishing. Galley trash can door adjustment. Installing edge trim details to house accent lighting. Potted inserts are being installed on the galley trash can.








water plumbing
Test run of all pluming equipment on the bench. Ensuring water flow is acceptable, water heater function, sink facet aerator function. work continues on the routing and installation of freshwater and wastewater lines. The tank dimensions have been developed. We have reached out for bids and are now considering whether to construct from stainless steel or plastic.





heating and air conditioning – november 20, 2024
Completing of fuel pluming to heaters, working on line routing and installation of fuel filters and pump/shutoff system. Initial test fitting of heater mockup. Consideration of ducting runs and ancillary equipment connections/locations.









electrical – november 20, 2024
Install of cabin systems terminal board on outboard side of galley. Building up circuit breaker panel. construction of wire harnesses for cabinetry and overhead crossovers.









interior – november 20, 2024
Continuing work on forward cabin headliner panels. Fabricating collar to close out edge of the astrodome. completing work on the flight deck door edge trim.






general updates – november 13, 2024
Interior panels continue to be covered, and the forward cabin headliner has been installed. Cabinetry continues to be prepped for finishes. Electrical work continues, and wiring for the main cabin bar has begun. The circuit breaker test panel has been laser cut to start populating the main cabin master wire harness. APU and heater fuel lines are being run and fit to the main R/H fuel tank. Baggage smoke elimination shutters have been removed for re-work and and are ready to be reinstalled. Liquor cubby has been modeled in CAD and the penetration made into the aft lavatory bulkhead.























general updates – november 6, 2024
Wiring for the main cabin systems is being prepped. Work on the airstair electrical system is in progress. Work in the baggage pit for fresh and waste water plumbing continues.












interior updates – october 30, 2024
Prep work continues on main cabin and conference room cabinetry prior to finishing and metal veneers being installed. Work on the valances in preparation for PSUs and coverings continues. Vibration isolators are being fitted to the main cabin bar. Conference room credenza is going through final fit and finish. The credenza top has been cut and prepped for finishing and mounting, images have been sent to the printing company for the printed leather inserts. Forward cabin headliner and galley headliner are in work. Wiring diagrams for the main cabin are being drawn up and wire runs/troughs are being built to accept the harness.
























interior updates – october 23, 2024
The channel for rerouting the fire protection pulleys is in work, and subfloor work is being done to accommodate this change around the hatch to the baggage compartment. The blackwater tank is in progress. Drink rail structure has been installed in the main cabin to make final adjustments and get final measurements for dress coverings, electrical and countertop material. Aft lavatory cabinetry is well into work and taking shape quickly. Galley and forward lavatory cabinetry is being prepared for finishes and their painted/riveted veneers. All cabin wash lighting fixtures have been installed and valances are being prepped for PSU’s and coverings. Custom door edge extrusion has been received on the shop floor and fitment checks are being made before the full run is produced. The last cushion for the state room divan is in work.





















interior updates – october 16, 2024
The fresh and waste water systems are being mocked up in the baggage compartment. Supports in the floor structure are being installed for the hatch to the baggage compartment. Overhead blankets in the forward cabin are being patterned. Work on the overhead valence panels continues. Work on the drink rails is in progress.














interior updates – october 9, 2024






























interior updates – october 2, 2024
Installation of leather and laminate continues. The astrodome frame has been trimmed to be flush with structure.















interior updates – september 25, 2024
Work on the stateroom divan continues. The seat covers are being manufactured and test fit. The bottom cushions have been completed. Tanks for potable and waste water systems are being mocked up in the sub-floor. Hardware, leather and laminate installation on drawers and cabinets throughout the galley, main cabin, and stateroom continues. Aft lavatory vanities are being assembled.


























Aft coat closed exterior leather application






interior updates – september 18, 2024
Work on the cabinets continues, with panels being covered and drawers having hardware fit.









INTERIOR UPDATES – SEPTEMBER 12, 2024
Cabinet liners are being manufactured and covered for galley cabinets, coat closets, and the stateroom cabinet. Work on the main cabin bar continues. Panels for the aft lavatory are being formed.

















interior updates – september 4, 2024
The aft cabin coat closet and door are being test fit. The main cabin overhead valences are being fit with their new mounting hardware and trim pieces. Laminate installation on the cabinet and credenza drawers continues.















general updates – august 28, 2024
Foam trim pieces and additional hardware are being installed on the main cabin overhead valence panels. Work continues on the aft coat closet and stateroom cabinetry. Laminate continues to be installed in the conference room credenza drawers. Main cabin blankets are being trimmed. The stateroom divan covers continue to be made and test fit.





















general updates – august 21, 2024
Work on the galley drawers and conference room credenza drawers continues, with laminate being installed. The stateroom cabinet is in work, as is the main cabin coat closet. Main cabin overhead valences are having hardware installed and being fit to their mounting brackets in the aircraft.

















general updates – august 13, 2024
Trim pieces for the gutters for the valences are being test fit. Vibration isolation is being installed on the aft lavatory bulkheads. Work on the stateroom divan continues, as does work on the aft cabin coat closet.












general updates – august 7, 2024
Trim pieces for the galley and main cabin are being manufactured and test fit. Work on the airshow bar continues, with potted inserts being installed. Subfloor work for cabin air system ducting is in work.









general updates – august 5, 2024
Work is in progress on drawer glides for the conference room credenza. The lavatory installation is being test fit. The stateroom cabinets are being test fit, and work on the divan continues. Laminate is being installed in galley drawers. Work on galley and conference room blankets continues.











General updates – July 24, 2024
Drawers for main cabin are being constructed. Materials for conference room are being prepared. Galley is being installed for fitting. Stateroom divan being test fitted and patterned.










general updates – june 12, 2024
Laminate is being installed on the galley drawers. The conference room credenza is being finished with leather.










general updates – may 30, 2024
Work on cabinets, drawers, and drawer faces continues, with latching mechanisms being installed and edges being matched. The aft lavatory interior bulkhead is being test fit and trimmed.







general updates – may 22, 2024
Latching mechanisms are being installed in stateroom cabinetry and bar drawers.







general updates – may 2, 2024
Work continues on the stateroom cabinetry and bar drawers. Forward cabin side panels are being upholstered.














general updates – april 24, 2024
The final carpet has arrived. A mock-up of the flight attendant seat frame is being built. Work on the stateroom cabinets and bar drawer faces continues. Forward cabin side panels are being trimmed down for covering, and foam and canvas are being cut for the side panels.









general updates – april 18, 2024
The Connie has returned from her trip to Sun n’ Fun and is back in the hangar. The bar drawer faces are almost ready for latches. The stateroom cabinet and the main cabin credenza are in work.